Railroad Canyon Rd Widening Project - Saturday Work Planned

Lane Closures and Construction to Cause Delays, Caution Urged

Post Date:02/08/2019 12:35 PM

Project Update: Week of February 11, 2019 

This week, crews were able to complete preparations for curb and gutter on the Eastbound side of Railroad Canyon Road.

However, due to continued poor weather conditions, weekend work is planned for the Railroad Canyon Road Widening Project on Saturday, February 9th from approximately 7 am. to 2 p.m. Crews will be on site grading and doing what they can to prepare for potential rainfall to protect the work completed and prevent erosion. One lane may be closed on the Eastbound side between approximately 7 a.m. to 2 p.m.

Next week, work will begin to construct curb and gutter on the Eastbound side. In addition, work is expected to begin on milling and paving. Single lane closures are anticipated with at least one lane open in each direction at all times.

REMINDER: Slow for the cone zone. Please remain vigilant of posted speed limits and be cautious in construction zones.

Project Update: Week of February 4, 2019

Recent weather events have caused significant delays on this project. Next week, crews will continue demolition work, primarily on the Eastbound side of Railroad Canyon Rd. However, rain is expected possibly Monday and Tuesday.

Lane closures are anticipated on both sides of the roadway, with one lane open at all times in each direction.

The City of Lake Elsinore and the City of Wildomar are partnering to make Lost Road a safer alternative, particularly for Canyon Hills residents. Asphalt removed from Railroad Canyon Rd. will be used to improve Lost Road. However, Lost Road is not a permanent roadway and commuters should remain cautious. This work is expected to begin in a few weeks.

The City would also like to urge commuters to place close attention to the posted speed limits, which do vary along the roadway particularly in the construction zones. Please remain vigilant of these speed limits and be cautious for your safety and the safety of work crews.

Project Update: Week of January 28, 2019

Last week, all work on the Railroad Canyon Road Widening Project was resumed after previous weather delays.

Project Work: This week, drainage modifications are expected to begin on both sides of the roadway. Southern California Edison (SCE) will also continue the relocation of five power poles to the Eastbound side of the road.

Lane Closures: At this time, the City is still anticipating a single lane closure on both sides of the roadway, i.e. Eastbound and Westbound sides. One lane will remain open in each direction at all times.

Alternate Routes: Lost Road via Bundy Canyon, Hwy 74 to Greenwald for Canyon Lake Residents, and Hwy 74 or Bundy Canyon Road to Interstate 215. 

Project Update: Week of January 21, 2019

Last week, all work on the project was delayed due to the significant rain received. Next week, we hope to resume all previously planned activities.

Project Work: Milling work is expected to begin on the Westbound side of Railroad Canyon Road and Southern California Edison will begin its process to relocate five power poles on the Eastbound side of the road.

Lane Closures: At this time, the City is anticipating a single lane closure on both sides of the roadway, i.e. Eastbound and Westbound sides. One lane will remain open in each direction at all times. Commuters are urged to remain patient and observe posted signs.

Interested in the what's happening with the Railroad Canyon Road Interchange? An update will be shared with the City Council on Tuesday, Jan. 22nd at approx. 7:00 p.m. Watch it live or later at www.lake-elsinore.org/live.

Project Update: Week of January 14, 2019

The Railroad Canyon Road Widening Project is now well underway. Next week milling will begin on the roadway and Southern California Edison (SCE) will start the relocation of five power poles on the Eastbound side of the road.

As a result, next week (January 14 – 18th) the City is anticipating that one lane may be closed at various times and locations on both sides of the roadway during construction hours (i.e. Monday – Friday, 7 a.m. to 4 p.m.) One lane in each direction will remain open at all times.

Rain is forecasted Monday through Thursday. If it rains, it may halt construction and cause delays for the project. 

Original Post: January 4, 2019 

On Monday, January 7th, construction will officially begin on the Railroad Canyon Road Widening Project. 

This project will expand the roadway to three lanes of traffic in each direction between Grape Street and Canyon Hills Road and includes pavement rehabilitation. The project will also include the relocation of utility infrastructure, the creation of improved drainage systems, safety improvements and a full rehabilitation of the roadway. 

Construction hours will be from 7 a.m. to 4 p.m. Monday through Friday and will require lane closures at periodically throughout construction. When lane closures are required, one lane will remain open at all times. There may be some exceptions. Whenever possible, intersection work or more substantial closures will take place at night between the hours of 8 p.m. and 4 a.m. Construction is expected to begin first on the Westbound side of Railroad Canyon Road. 

Road and lane closures will be determined on an ongoing basis. The City will be sure to post information regarding planned closures whenever possible. Commuters are urged to allow themselves additional time and/or to choose alternate routes during construction to avoid significant delays due to construction.

Alternative routes include Lost Road via Bundy Canyon for Canyon Hills Residents, Hwy 74 to Greenwald for Canyon Lake Residents, and Hwy 74 or Bundy Canyon Road to Interstate 215. 

Sign up for email notifications for project updates. 

In addition, the City is making significant progress on the future improvements to I-15/Railroad Canyon Road Interchange, which is expected to be under construction in early 2020. 

Project Limits

Project Name: Railroad Canyon Road Street Widening/Pavement Rehabilitation Improvements

Project Location: Railroad Canyon Road between Grape Street and Canyon Hills Road

Construction Hours: Monday - Friday, 7 a.m. to 4 p.m. 

Project Impact:

  • Construction hours Monday through Friday from 7 a.m. to 4 p.m. 
  • Westbound Construction Expected January - March 2019
  • Eastbound Construction March - April 2019
  • When a lane closure is in place, one lane will remain open at all times (with some exceptions)
  • Night construction, when needed, will occur between 8 p.m. to 4 a.m. 
  • Construction hours and schedule is subject to change

Project Description:

  • Widening and Striping 3 Lanes of Traffic in Each Direction Between Grape Street and Canyon Hills Road.
  • Drainage Modification to Accommodate Widening 
  • Rehabilitation of Existing Pavement includes Slurry Seal, 2" Mill and Overlay and Full Depth Reconstruction 
  • Safety Improvements 
  • Utility Relocation and Co-Op Agreements
    • Southern California Edison (SCE): Location of 5 Guy Poles
    • Eastern Municipal Water District (EMWD): Relocation of Valves and Manhole Adjustment to Grade
    • Elsinore Valley Municipal Water District (EVMWD): Relocation of Appurtenances and Grade Adjustments
    • SoCal Gas: Valve Adjustments to Grade

Design Completed: September 2018 

Construction Start Date: January 7, 2019

Estimated Completion Date: Substantial completion expected by the end of April 2019, but this date is subject to weather or other unforeseen delays. 

Contractor: All American Asphalt 

Future Improvements; The City continues to make significant progress on the critical I-15/Railroad Canyon Road Interchange improvements.  The Final Environmental Document has been approved by Caltrans and the project is currently in the Plans, Specifications, and Estimate (PS&E) phase. The PS&E Phase will provide contract documents to be advertised and let out for bid. The City has studied and considered several alternatives and has decided to proceed with Alternative 2 in Phase I. Construction is expected to begin in early 2020 with completion by 2022. Find out more. 

Project Documents: 

Fact Sheet - Project Update February 8, 2019

Fact Sheet - Project Update February 1, 2019  

Fact Sheet - Project Update January 25, 2019 

Fact Sheet - Project Update January 18, 2019 

Fact Sheet - Project Update January 11, 2019

Fact Sheet - Project Update January 4, 2019

Project Information Sheet 

PowerPoint Update regarding Railroad Canyon Rd. Interchange & Widening Project  - July 2018

PowerPoint Update to City Council regarding Railroad Canyon Rd. Interchange - January 2019

Find out more about other City Construction Projects.

Questions or Concerns: 

If you have any questions or concerns related to this project, you may complete our Railroad Canyon Road Widening Project Online Comment Form or contact the Railroad Canyon Road Widening Hotline at (951) 674-1344.

Sign up for the email notification list for updates regarding this project.  

 