Summerhill Drive Paving Project Begins July 15th

All construction to be completed at night.

Post Date:07/08/2019 2:21 PM
Project Update for Week of July 22; 

Next week from July 22nd to July 26th, construction work will be done during the day from 7 a.m. to 4 p.m.

The project is still expected to be fully complete by July 30. This project includes the full reconstruction and repaving of Summerhill Drive from Railroad Canyon Road to Canyon Estates Drive.

Project Description: 

Full reconstruction and repaving of Summerhill Drive from Railroad Canyon Road to Canyon Estates Drive. All work will be completed at night. The grinding and reconstruction of the road is expected to take six nights with the striping of the roadway taking approximately two nights. Weekend work may also occur at night to complete the project as soon as possible. However, this is dependent on the contractors availability. The project will be fully complete by the end of the month. 

Location: Summerhill Drive from Railroad Canyon Road to Canyon Estates Drive

Construction Hours: Night hours only from 8 p.m. to 4 a.m. from Monday thru Saturday (Subject to Change).

Construction Start Date: July 15, 2019

Estimated Construction Completion: July 30, 2019

Contractor: All American Asphalt 

 