Lincoln St. Pavement Rehabilitation Project

Project is funded by SB 1 Gas Tax.

Post Date:07/18/2019 3:31 PM

In August, the City of Lake Elsinore kicked off yet another critical roadway project that is going to greatly improve the safety and appearance of our community - the Lincoln Street Pavement Rehabilitation Project. 

Project Description:

  • Entire rehabilitation of Lincoln Street and Parkview Drive, approximately 2.8 miles of roadway.
  • Pavement rehabilitation includes grinding, asphalt paving, slurry sealing, crackfill, concrete work and new striping.
  • More specifically, as shown in the exhibit below, this project will include portions of the roadway that will be a full reconstruction (grind & overlay) and others that will only require a new coat of asphalt (slurry seal).
    • Lincoln Street from Riverside Drive to Machado Street - Grind & Overlay
    • Lincoln Street from Terra Cotta to Grand Avenue - Grind & Overlay
    • Parkview Drive - Grind & Overlay
    • Lincoln Street from Machado Street to Terra Cotta Street - Slurry Seal
    • Grand Avenue to Dale Court - Slurry Seal

Location: Lincoln Street from Riverside Drive to Dale Court & Parkview Drive from Machado Street to Parkview Drive 

Construction Start Date:July 22, 2019

Estimated Construction Completion: Late August 2019

Estimated Cost: $1 Million - funded by SB 1 Gas Tax Dollars 

Contractor: All American Asphalt 