CONSTRUCTION UPDATE: Dexter Avenue Rehabilitation, Central Avenue to Second Street

Allow extra time for travel during rehabilitation of roadway.

Post Date:04/27/2009

Project paving will begin June 1st and continue through June 5th.  Completion including Signing, striping and shoulder work is on schedule to be completed by June 15th.

  • Project Name:    Dexter Avenue Rehabilitation
  • Project Purpose:  To repair deteriorated pavement on Dexter Avenue from Central Avenue (Hwy 74) south to Second Street.  Construction includes a portion of Second Street.
  • Construction Period:  Construction began on approximately April 13th and is scheduled to complete on June 15, 2009.
  • Anticipated Delays:  Reduced speed and extra caution due to construction activity will be the primary cause of delays.
  • Anticipated Detours/Road Closures:  None.  Two lanes will be open to traffic on Dexter Avenue during construction; traffic control devices will be set up directing drivers to use a compacted shoulder and one paved lane.  
  • Project Point of Contact: For questions or comments regarding this project, please contact Dave Solomon at 951-674-3124 x 242.

 Dexter 2

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer