Lake Elsinore Advanced Pump Storage Project (LEAPS)
Most Recent Project Update
Project Update: As of October 14, 2022
The Bluewater Renewable Energy Storage Project, formerly known as the Lake Elsinore Advanced Pump Storage Project or LEAPS, will be hosting an Open House at the Lake Community Center (310 W Graham Avenue) to inform the community about the latest changes to the project and to gather feedback. The event is Saturday, October 15, 2022 from 9 am to 2 pm.
View the October 15 meeting invite (PDF).
About the Proposed LEAPS Project
The LEAPS Project is a hydroelectric project, which consists of an upper and lower reservoir with a set of tunnels running between them. When electrical energy is in high demand, the water in the upper reservoir is released through tunnels flowing down to turbines at the powerhouse. The upper reservoir becomes, in effect, a source of stored energy.
For LEAPS, the Lake would serve as the "lower reservoir" and the upper reservoir would be constructed in the Cleveland National Forest at Decker Canyon (just south of State Route 74). The pump/powerhouse facility would be located near the Lake on the west side of Grand Avenue in the Lakeland Village area (and is typically referred to as the Santa Rosa Powerhouse). To power the pumps and deliver the generated electricity onto the state's electrical grid, LEAPS also involves the construction of approximately 32 miles of 500 kV transmission lines and towers.
The project applicant, Nevada Hydro, has proposed a grid interconnect near Lee Lake to the north. The transmission lines will travel south largely within the Cleveland National Forest and connect to the powerhouse. The powerhouse will also be connected by 500 kV lines and towers traveling further south primarily through the National Forest to an interconnect point adjacent to Camp Pendleton. The 500 kV lines in the general vicinity of the powerhouse will be undergrounded.
LEAPS is designed to generate approximately 500 megawatts (MW) of electricity typically lasting 12 hours. By way of comparison, the former San Onofre nuclear facility could produce approximately 2,150 MW.
Nevada Hydro is currently seeking a permit to operate LEAPS from the Federal Energy Regulatory Commission (FERC). While the City is fully participating in the formal FERC licensing process, concerns remain about coordinating the efforts of federal agencies which the City believes have a shared interest in improving the Lake and ensuring that federal agencies fully understand the City's position and concerns related to the project.
The City of Lake Elsinore continues to monitor and inform our community as this project makes its way through the federal approval process to ensure our best interests are protected.
Previous Updates
Project Update: As of August 18, 2022
On August 18, 2022, LEAPS Hydro Company provided an update at the Lake Elsinore and San Jacinto Watersheds Authority (LESJWA) Board of Directors Meeting. At the meeting, it was announced that the project is under new ownership by Bluewater Renewable Energy LLC, the owner of Nevada Hydro Company. Additionally, the project has changed its name to Bluewater Renewable Energy Storage Project.
View the full August 18, 2022 presentation (PDF).
Project Update: As of December 14, 2021
On December 9, 2021, the Federal Energy Regulatory Commission (FERC) notified Nevada Hydro (PDF) of the dismissal of their licensing application. The letter states that "if an applicant fails to provide timely additional information, the application may be dismissed." As a result of Nevada Hydro not providing the requested information, the licensing application was dismissed. Nevada Hydro has 30 days to submit a request for a hearing for reconsideration of the dismissal. In addition, Nevada Hydro may refile the application with all requested information. The City is now waiting for Nevada Hydro's response to this latest update and will respond appropriately.
Project Update: As of April 13, 2021
The City submitted its response to the State Water Resources Control Board's Request for Comments regarding the Notice of Preparation and Scoping Meetings for an Environmental Impact Report. The State Water Resources Control Board will ultimately require an Environmental Impact Report before issuing any associated water permits with the LEAPS project. Read City of Lake Elsinore's Comments, dated April 13, 2021 (PDF). View the Waterboard's project page.
Project Update: As of September 2020
On August 27, 2020, the Federal Energy Regulatory Commission (FERC) issued a Notice of Anticipated Schedule for Lake Elsinore Advanced Pumped Storage Project (LEAPS). At this time, FERC is projecting it would issue its Final Order on March 17, 2022. Review the latest schedule provided by FERC. Please note, this schedule is subject to change.
Project Update: As of August 17, 2020
The City submitted a comment letter to the Federal Energy Regulatory Commission (FERC) related to Scoping Document 1 for the Lake Elsinore Advanced Pump Storage Project. See the City's Comment Letter (PDF).
Project Update: As of July 30, 2020
In response to FERC's Scoping Document, the City hosted a LEAPS Virtual Community Workshop on Thursday, July 30, 2020 at 6 pm via Zoom.
View the PowerPoint from the July 30 workshop (PDF).
View the flyer for the July 30 event (PDF).
Nevada Hydro, the LEAPS Project proponent, did not present during the LEAPS Virtual Community Workshop, but has provided the following handout for attendees:
Nevada Hydro - LEAPS Handout, July 30, 2020 (PDF)
Project Update: As of July 14, 2020
On June 18, 2020, Federal Energy Regulatory Commission (FERC) issued a Notice of Intent to Prepare an Environmental Impact Statement and Soliciting Scoping Comments. Unfortunately, due to COVID-19 concerns, FERC will not be hosting a local public scoping meeting for our community.
View Notice of Intent to Prepare an Environmental Impact Statement and Soliciting Scoping Comments (PDF)
View Scoping Document 1 for Lake Elsinore Advanced Pumped Storage Project Number 14227 (PDF)
FERC is soliciting comments to the Scoping Document by August 17, 2020. Citizens can submit their comments in various ways including:
- Electronic filing
- Brief comments of 6,000 characters or less
- Send paper comments to:
Secretary, Federal Energy Regulatory Commission
888 First Street, NE
Washington, D.C. 20426
All comments should clearly identify the project number on the first page - LEAPS Project (P-14227-003). Read more about how you can comment on FERC's Notice of Intent (PDF) and Scoping Document (PDF).
The City in partnership with Riverside County will be hosting our own LEAPS Virtual Community Workshop to allow our citizens to learn more about the LEAPS project, the FERC and Scoping Process, and how you can submit comments.
On Tuesday July 14, 2020, staff provided City Council with an update on this project (PDF).
Project Update: As of August 30, 2019
Today, the City filed its motion to intervene and comments with the Federal Energy Regulatory Commission (FERC). FERC is soliciting motions to intervene and protests as stated in their notice (PDF) dated July 26, 2019.
The deadline for filing motions to intervene and protest is 60 days from the issuance date of the notice (PDF), or September 24th (this is a correction for another deadline of October 1st the City previously estimated).
As stated in the notice, "the Commission strongly encourages electronic filing. Please file motions to intervene and protest using the Commission's eFiling system. For assistance, please email FERC Online Support or call 866-208-3676 (toll-free), or 202-502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P-14227-003."
Motion to Intervene by the City of Lake Elsinore (PDF)
Project Update: As of August 7, 2019
In January, Dr. Michael A. Anderson, Ph.D., completed a final report on behalf of Nevada Hydro Company for submittal to the Federal Energy Regulatory Commission (FERC) regarding the "Impacts of the Lake Elsinore Advanced Pumped-Storage (LEAPS) Project on Water Quality in Lake Elsinore." As the stewards of the Lake and recognizing its value to our community, the City hired a qualified water quality consultant, Stillwater Sciences, to conduct a peer review of this report.
During this review, Stillwater Sciences identified several deficiencies in the report. Specifically, the peer review summarized its finding by stating "because of the short periods analyzed, incomplete documentation of model uncertainty, and the inclusion of other factors unrelated to LEAPS (e.g., initial SWP supplementation, O2 additions), the report does not provide a clear water quality assessment of LEAPS operations over the long-term."
On Friday, August 2, 2019, the City submitted a cover letter and a full copy of this peer review to FERC to express concerns regarding the final report and the City's concern that this study and others routinely downplay and minimize the impacts of the LEAPS project on Lake Elsinore and the surrounding communities. The City has requested that FERC require Nevada Hydro to correct the deficiencies found by Stillwater Sciences in this final report on water quality.
- Impacts of the Lake Elsinore Advanced Pumped-Storage (LEAPS) Project on Water Quality in Lake Elsinore (Final Report) (PDF) by Dr. Michael A. Anderson, Ph.D., January 30, 2019
- City of Lake Elsinore Cover Letter and Stillwater Sciences Peer Review as submitted to FERC (PDF)
Project Update: As of August 2, 2019
On July 26, 2019 the Federal Energy Regulatory Commission (FERC) officially accepted Nevada Hydro Company's application for the Lake Elsinore Advanced Pump Storage Project, known as LEAPS. This action means that Nevada Hydro has now submitted certain required information and resolved deficiencies previously identified by FERC. Although the application was accepted for filing, FERC has not made any decision approving LEAPS. That decision-making process will take place over the next 18 to 24 months.
At this time, the next major step for FERC is to issue a "notice of intent" to prepare an environmental impact statement and will include setting dates for local workshops known as "scoping meetings" sponsored by FERC and open to the public. At least one workshop will be held in the City to ensure our citizens have the opportunity to express their concerns related to this project. The City anticipates that this notice will be issued in the fall but FERC has not made public a permitting timetable. Once prepared, the environmental impact statement process will include an opportunity for the public to submit comments and concerns.
In April, the City Council unanimously voted to take a formal stance "to oppose the LEAPS project subject to conditions." See update from April 2019. Last month, the City sent a thorough comment letter to FERC addressing legal concerns related to Nevada Hydro's application and inconsistencies with existing City agreements related to the Lake's management including the lake level. The City will continue to engage directly with FERC in order to educate the Commission about our concerns and project impacts on our Lake and the community.
FERC's July 26, 2019 notice also solicits motions to intervene and protest. Intervention is not required for a citizen to comment on the project but is required if the person desires to later challenge FERC's decision on the project in court. The deadline for submitting motions to intervene and protest is 60 days from the date of the notice. Persons interested in intervening in the proceeding should review the notice (PDF), which sets out the basic requirements. Additional information is available on FERC's website.
City of Lake Elsinore Comment Letter - June 25, 2019 (PDF)
Project Update: As of July 2019
In June, the City's Energy Subcommittee Mayor Steve Manos, Councilmember Natasha Johnson, staff and our consultant team traveled to Washington, D.C. to educate and engage our federal agencies and elected officials about the City's opposition to the proposed Lake Elsinore Advanced Pump Storage Project (LEAPS).
While there, our City team met with several officials from a variety of agencies, committees and congressional seats to discuss and advocate on behalf of the community related to LEAPS including water quality, water quantity, the dynamic and complex nature of our Lake, and the importance of this project to our entire community. Something the City emphasized throughout our trip is the history of the lake and a state mandate that requires the City to maintain the lake as recreational body of water in perpetuity.
Overall, the trip was successful and assured us that the City has taken all the steps necessary to ensure that our voice will be heard as the process unfolds. Most encouraging from the trip was the Federal Energy Regulatory Commission's (FERC) willingness to conduct a LEAPS meeting in Lake Elsinore for residents as well as their interest in keeping the City informed.
At this time, there are no actions necessary for the City or the community. However, the City will be sure to share any and all appropriate opportunities to submit comments to FERC or others regarding this project.
As a reminder, the City took a formal position of opposition in April subject to conditions (see April update below) and will continue to work on behalf of protecting our community.
Next Step for the Project: The project is still in the midst of the federal licensing process with the Federal Energy Regulatory Commission (FERC). Nevada Hydro has a deadline to submit all additional studies and information as requested by FERC by June 30, 2019.
Project Update: As of April 2019
For the last couple of years, the City of Lake Elsinore has taken a proactive approach to understanding the Lake Elsinore Advanced Pump Storage (LEAPS) project proposed by Nevada Hydro. The City has actively advocated for more detailed studies and explanations concerning the project's impacts on the Lake and the community.
On April 9, 2019, the City Council unanimously voted to take a formal stance "to oppose the LEAPS project subject to conditions."
During the meeting, the City received comments from City staff and the community. Key concerns expressed centered on impacts to the Lake including water quality, fluctuating Lake levels, the fishery, ecology, and shoreline impacts. Other concerns raised included the potential for disasters if a proposed dam for the project's "upper reservoir" in Cleveland National Forest were to fail, fire hazards from the proposed 32-mile segment of high-powered transmission lines, the impact on wildlife, the overall impact to the aesthetics of the community and the Lake, and the potential for property damages and acquisitions.
The City Council urged Nevada Hydro, the project proponent, to give serious consideration to these concerns and to provide additional project details, including actual and measurable public benefits.
The City is willing to continue dialogue with Nevada Hydro, but is seeking meaningful answers and solutions to concerns related to the project. While LEAPS could have the potential to improve Lake Elsinore, there are far too many unknown and potentially negative impacts to the Lake and the community at this time.
For these reasons, the City Council urged Nevada Hydro to act in good faith and provide clear, positive benefits to the City of Lake Elsinore.
More Information:
- Council Meeting Webcast video
- April 9, 2019 City Council Meeting Agenda (PDF)
- April 9, 2019 Staff PowerPoint Presentation (PDF)
- Valley News Article re: City Council Decision
June 21, 2018 Update
On Friday, June 15, 2018 the Federal Energy Commission (FERC) responded to the additional study requests (PDF) from the City and eight other resources agencies. The City submitted its request for additional studies (PDF) on December 1, 2017.
Additional study requests by the City included: updating Geotechnical reports, updating Biological Resource Study, Shoreline Erosion and Turbidity Study, Recreational Needs, Effect of Daily Lake Elevation Fluctuations on Existing Recreation Facilities, updating and expanding Visual Simulations, updating Cultural Resource Assessment, updated Construction Traffic Analysis, Noise and Vibration Assessment, and a Property Value Assessment.
The City was able to successfully argue and convince FERC to require additional studies related to the geotechnical impacts, some water quality, aesthetic impacts, traffic and cultural resources. The others were denied. Other studies approved as requested by other agencies included seismic hazard, total nitrogen, phosphorus, and cyanotoxin, operation efficiency and water quality, updated surveys for federally threatened and endangered species, vegetation mapping study plan, fire study and alternative transmission alignments.
The deadline for Nevada Hydro to submit the additional studies is set for September 13, 2018.
January 18, 2018 Update
On Monday, January 8th the City received a copy of a Deficiency of License Application and Request for Additional Information letter (PDF) sent to The Nevada Hydro Company regarding their proposed Lake Elsinore Advanced Pump Storage (LEAPS) Project.
The letter was sent by the Federal Energy Commission (FERC) and states that Nevada Hydro's application was not complete (i.e. does not conform to the requirements of the Commission's regulations) and requested additional information.
Among the additional information requested, FERC asked Nevada Hydro to identify a specific source of water to maintain the operational level of Lake Elsinore above 1240 feet, assess the availability of water, and coordinate with the Elsinore Valley Municipal Water District and the City of Lake Elsinore to develop a reservoir operation plan for related to the ongoing operation and maintenance of the Lake.
Nevada Hydro has 90 dates from the date of this letter, January 3, 2018, to respond to the letter.
December 12, 2017 Update
City staff provided an update (PDF) to our City Council about the LEAPS project proposed in and near our City.
In addition, the City Council approved an agreement for government relations and legislative advocacy services in Washington DC to regularly monitor this project and advocate on behalf of the City to ensure our community's best interests are protected as this project makes its way through the federal licensing process. This includes engaging the congressional delegation and federal agencies to raise awareness about the project and its potential impacts to our community.
December 21, 2017
The Nevada Hydro Company issued its response to study requests (PDF). The deadline to file additional study requests with FERC was December 1, 2017. The City did issue a request for additional studies.
City Comment Letters & Documents
- Comment Letter to State Water Resources Control Board - April 13, 2021 (PDF)
- Comment Letter to FERC - August 17, 2020 (PDF)
- Timeline of Key Activities (May 2017 to December 2019) (PDF)
- Motion to Intervene by the City of Lake Elsinore (PDF)
- Comment Letter and Stillwater Sciences Peer Review as submitted to FERC (PDF)
- Comment Letter to FERC - June 25, 2019 (PDF)
- April 9, 2019 City Council Meeting
- Council Meeting Webcast video
- April 9, 2019 City Council Meeting Agenda (PDF)
- April 9, 2019 Staff PowerPoint Presentation (PDF)
- Valley News Article re: City Council Decision
- Comment Letter - Request for Additional Studies - December 1, 2017 (PDF)
- Staff Update Presentation on December 12, 2017 (PDF)
- Staff Report from December 12, 2017 (PDF)
Additional Project Information
- FERC Licensing Application Dismissal Letter (PDF)
- State Water Resources Control Board LEAPS Project Page
- FERC Notice of Anticipated Schedule for LEAPS (PDF)
- Notice of Application Accepted for Filing and Soliciting Motions to Intervene and Protests (PDF)
- LEAPS Regional Vicinity Map of Project including Transmission Line (PDF)
- Proposed Location of Powerhouse Substation and Inlet/Outlet (PDF)
- Impacts of the Lake Elsinore Advanced Pumped-Storage (LEAPS) Project on Water Quality in Lake Elsinore (PDF) (Final Report) by Dr. Michael A. Anderson, Ph.D., January 30, 2019
- FERC's Letter regarding Deficiencies and Request for Additional Information to The Nevada Hydro Company (PDF)
- Nevada Hydro Company's Response to FERC's Deficiency and Information Request - April 3, 2018 (PDF)
- Nevada Hydro Response to Study Requests to FERC (PDF)
- Advanced Pump Storage - Basic Components (PDF)
- FERC Hydropower Licensing Process (PDF)